Project learning journey

Monash Medical Centre Tower Expansion · how delivery unfolded, what sat underneath it, and what to do next time

KEY Worked well Pressure point Decision or milestone System condition underneath Intervention (lesson), from participants Intervention (lesson), added by Opposite LL-007Lesson code: find the light bulb with the same code Finding to the system condition underneath (lines join where findings share one) Earlier cause to later problem (green: good practice carried forward) 1Worked example Columns are review stages. Procurement and delivery overlapped in time.
STAGE Click a stage heading or number to zoom in. Click anything for its detail. Drag or scroll to move; pinch, Ctrl and scroll, or the + and − buttons to zoom.
WHAT PEOPLEEXPERIENCEDDECISIONS ANDMILESTONESWHAT THE SYSTEMWAS DOINGFUTURE-PROJECTINTERVENTIONSRequirements still open in design came back as an FF&E overrun just before tenderSafety plan requirements not set out at tender led to round after round of reviewA new way of working without agreed process, again, for Group 1A equipmentThe disruption notice routine carried over into main worksSTAGE 1Design developmentSTAGE 2Enabling works procurementSTAGE 3Main works procurementSTAGE 4Enabling works deliverySTAGE 5Main works delivery, design and FF&ERequirements were stillsettling as the designdevelopedLL-007The design team knewhealthcareLL-005Users tested the designat full scaleLL-003The design was endorsedwith items still openLL-008Safetyrequirements werenot set out up…LL-015A simple contractsuited a smallpackageLL-013Early contractorsite knowledgecarried into…LL-011A new contractform, learned onthe jobLL-021The procurementtimeline wasagreed and keptLL-020Tender went out ona well-developeddesignLL-022The health servicewas active on theevaluation panelLL-023A long approvalspath to awardLL-024Disruption noticesreviewed on weeklysite walksLL-026The safety planwent through roundafter roundLL-030Helipad andambulance changesplanned earlyLL-027Disruption noticesbecame a reliableroutineLL-035FF&E funding and thetransfer list werenot fixed earlyLL-044No agreed way toselect Group 1AequipmentLL-045Problems raisedearly, contract runin good faithLL-033Client staff on sitesettled issues atproject levelLL-034Fumes reached thewardsLL-038Unknown services andsite conditions keptsurfacingLL-040An agreed fast pathgot urgent workthroughLL-042The health servicewas in FF&E planningearlyLL-041Design reviews aretaking longer thanplannedLL-043Jul 2024Design development startsJul 2025Design development endorsedwith conditionsJan to Feb 2025Enabling works tenderopen20 Jun 2025Enabling workscontract executedAug 2024Enhanced designand constructmodel agreed11 Dec 2025Initial WorksOrder23 Jan 2026Gate 4 tenderdecision23 Mar 2026Main workscontractexecutedEarly Jun 2025Construction starts18 Dec 2025Practical completionJan 2026Site possessionby Jun 2026Design consultant novationfinalisedApr 2028Stage 1 completion forecastClinical and user engagement wasthorough10 of 10 rated it a top impact · CF12LL-003Requirements were not settled beforedesign and tender15 of 21 rated it a top impact · CF01LL-007Knowledge left when people left6 of 8 rated it a top impact · CF08LL-046New processes arrived before theguidance did8 of 9 rated it a top impact · CF03LL-017The hospital carries the impact but haslittle authority7 of 9 rated it a top impact · CF04LL-019Working together on site solvedproblems quickly27 of 29 rated it a top impact · CF06LL-034Open, trusting relationships betweenthe organisations11 of 11 rated it a top impact · CF05LL-033LL-003Full-scale userwalkthroughs, withright-sized groupsLL-005Define scope andgovernance for allparties at design startLL-007Settled requirements as agate before design closesLL-008Agree what endorsementmeans before sign-offLL-033Build in trust practicesand test them with apulse surveyLL-041Health service confirmsFF&E specifications earlyLL-046Plan continuity of keypeople, with a lessonsreview at each closeLL-011Carry early contractor site knowledgeinto the worksLL-013Match the contract form to the packagesizeLL-015Safety plan requirements written intothe tenderLL-017Guidance andtraining before anynew processLL-019Agreed stop-workroute before worksstartLL-020Agree the timeline,with delegates innegotiationsLL-021Sound out the marketon a new contractformLL-022Tender a lockeddesign with itsopen-items registerLL-023Active healthservice members onthe panelLL-024Map the approvalpath and pre-briefapproversLL-040Review exits andegress with thehospital before…LL-044Coordinate the FF&Eschedule beforetenderLL-026Joint site walks with every stakeholderLL-027Plan shutdowns early and combine themLL-030One joint review of the safety plan,with written guidanceLL-034Client and hospital staff onsite from day oneLL-035Restart interface meetingsat contract awardLL-038Check plant and air intakesbefore nearby worksLL-042Agree a fast path forpriority reviewsLL-043Set review times and packagecontent up frontLL-045Agree the Group 1A selectionprocess before it starts12345

How to read this map

Each column is a stage of the review. Every finding shown was rated among the biggest impacts by workshop participants; the vote counts are in the interactive version. Read down a column: what people experienced, the decisions and milestones, the system conditions underneath, and what to do next time.

Dotted teal lines link what people experienced to the condition underneath it. Where several findings share a condition, their lines join before reaching it. Dashed arcs trace an earlier cause to a later problem. The lesson code under each finding and system condition (for example LL-007) points to the light bulb with the same code in the interventions lane, and to the lesson in the register. A finding and the condition under it can have different lessons, so their codes can differ.

The map shows the key findings and the seven cross-project patterns rated highest. Every other finding is in the report appendix.

Follow the numbered thread: one worked example

    Each stage in a sentence

    Independent lessons learned review for VIDA Health by Opposite, November 2026. Findings describe conditions rather than people or organisations. Dates are from the project records as corrected in the workshops.